Friday 28 March 2014

Return Works & Ground Floor Shuttering

The small wall from inside the return was removed at the start of the week. It was impeding on the new bedroom/office to be build in its place:


First the wall above had to be supported:





The remains of the wall:


Plywood shuttering has to be created for the proposed floor works. The framework will contain an insulated concrete slab, surrounded by a breathable, insulated lime-crete slab. The underfloor heating will then be laid on top of both slabs, before a final screed is laid and the wooden floor boards reinstated:

The hallway:





The return:



Front and rear rooms:





Several tonnes of Leca Insufill arrives tomorrow!